Building Your Dream Home-- Part 3
Exterior Framing Continues
With the homes sub-floor down and the exterior walls framed and up, the framing team was on to the roofing system. Though the roofing system was rather easy in structure with simply a 12/12 pitch and no valleys it was a substantial framing endeavor due to simply the size and height of it. Your house was 32 feet large by 44 feet in length, and the outside side walls stood 11 feet tall in the terrific space. This outside wall height of 11 feet translated into a roofing ridge that was 27 feet off the floor of the terrific room. Consequently staging was required to set up the ridge pole and roofing system rafters. In addition, given that the period from the top of the walls to the ridge was so long, heavy 2x12s were required for the roof rafters. Within a week, nevertheless, the group had finished the installation of the roofing system rafters and the house started to handle real shape.
I needs to comment briefly about the sub-floor and exterior walls before I move on.
Regarding the outside wall framing I utilized 2 × 6 building and construction. This is typical in New England as the additional wall depth permits greater insulation elements; a should in cooler climates.
Sheathing the Outside of the Home
In order to get pipes and electrical professionals onto a website usually they want the home buttoned up. This includes the roofing system shingled and the doors and windows on. Therefore my framing crew moved onto the exterior sheathing once the walls and roof framing were complete.
As with the sub-floor, I once again selected plywood for the outside sheathing for the exact same factors pointed out earlier. On the outside walls outside grade plywood was used. On the roofing 5/8 exterior grade plywood was utilized. I understand lots of builders today use OSB for both the walls and roofing system, nevertheless, I still believe for stronger building plywood is the method to go.
The sheathing effort took about a week to complete. Throughout this time outside doors and windows appeared on the site. Staging the delivery of material lowers theft and insurance risk in addition to keeps a less chaotic building and construction site. Nevertheless, as I have indicated previously, interaction is vital when you are doing Just-in-Time material delivery.
Installing Exterior Doors and Windows
The setup of the doors and windows was a significant undertaking for this project as the lake profile of the home was actually a wall of windows; 32 feet in width and 27 feet in height. A lot of engineering had gone into the window design so that the 10 large custom windows would mesh like a jig saw puzzle. This said, when the windows arrived on site and were inspected, it was figured out that some of them were not built correctly to the dimensions defined. After much dispute with the framing crew, the window supplier and me we reached a compromise on sharing the expense of repairing the windows. The window vendor reclaimed the improperly sized windows and the framing team started the installation of the doors and what windows they could set up. Thankfully the window vendor had the ability to go back to the website with the properly sized windows within a couple of days and the building phase did not miss out on a beat.
Completing the Interior Framing
With the doors and windows installed, the framing team proceeded to complete the Interior Framing. This was an interesting time, as the rooms started to take real shape. You could now stroll down corridors and into bedrooms and closet areas. Within just a few days the interior walls were complete and the framing crew continued onto the roof for the common causes of clogged drain shingling.
I should keep in mind that 2 × 4 construction was used on the interior walls as insulation was not needed on the interior walls.
Shingling the Roof
The last job to finish before your house might be categorized as Buttoned Up was to install the shingles on the roof. Fortunately my framing crew was also able to do this job, thus removing the need for yet another subcontractor.
I picked a thirty years architectural shingle due to the quality and look I was attempting to attain on the home.
Though reasonably a basic roof, it was quite big and the weather condition was less than hospitable. Consequently it took nearly 2 weeks to complete this task. However, with the roofing total, my electric and plumbing professionals were now able to begin their work.
Also, with the primary home now structurally total, the framing crew moved onto the garage framing and building and construction phase. As an outcome of staging the garage behind the primary home construction stage, I was able to have subcontractors work in parallel without getting in each others way.
Rough Electric and Plumbing
With the house Buttoned-Up, my Electric and Plumbing subcontractors appeared to begin the roughing in phase of their respective tasks.
Rough Electric
I had met a few days before on site with the Electric subcontractor to talk about the positioning of all the wall outlets and switches, in addition to where the light fixtures would be positioned. Throughout our discussion he marked the wall studs for the placements of the electric electrical wiring boxes so that we might imagine the entire electrical electrical wiring scheme. We likewise marked where the telephone and cable television boxes would reside.
During the electrical rough in circuitry phase, the electrician set up all the wiring boxes and ran wire from the boxes to where the main circuit panel box would reside.
Rough Plumbing
As with the Electrical Subcontractor, I had actually met a number of weeks earlier with the Plumbing Contractor. Throughout this meeting we talked about the kind of heat for the home, as well as where the restrooms and kitchen area were to reside in the home. We likewise went over types of bathroom components consisting of tubs, sinks and toilets. As a result, when he showed up on website he new exactly where to run primary drain and supply pipes and vent stacks. He likewise roughed in all of the plumbing for each restroom and cooking area pipes cloggeed drain vic fixture.
Within a week both the Electrical and Rough Pipes professionals had actually finished their tasks and had effectively passed their particular evaluations.